Project update / September ( I )

1. Structural reinforcement for Mid Hall and Main Hall Men’s Restroom.
1-1. Blocking in Mid Hall Restroom and Storage.
Picture
Picture
Picture
1-2. Blocking in Main Hall Men’s Room.
Picture
Picture
1-3. Reinforcement in Main Hall Restroom.
Picture
Picture
1-4. The gaps between the roof and the wall between Main Hall and Men’s room needs to be filled with a 4x4 block.
Picture
Picture
1-5. The 4x4 needs to be shaped to fit into the gap.
Picture
Picture
1-6. Gaps between roof and exterior walls needs to be filled with blocking with holes for ventilation.
Picture
Picture
2. Electrical Wiring for North Hall.
Picture
Picture
Picture
Picture
Picture
Picture
3. Continuing installing fire sprinkler system.
3-1. North Hall.
Picture
Picture
Picture
Picture
3-2. Main Hall Men’s Restroom.
Picture
3-3. Mid Hall.
Picture
Picture
3-4. Mid Hall Restroom.
Picture
3-5. Main Hall Women’s Restroom.
Picture
Picture
3-6. Main Hall.
Picture
Picture
Picture
Picture
4. Demolition and removing the asphalt on the east side of the building.
Picture
Picture
Picture
Picture
Picture
Picture
5. Found an underground structure, and Building & Ground Deptartment is removing it.
Picture
6. Installing new roof drain/down spout in North Hall.
6-1. Roof Drains.
Picture
Picture
6-2. Secondary Downspout.
Picture
Picture