Project update / October ( II )
8. B&G continues working on bring utility to Project Site. 8-1. Fire Water Line.
9. Finishing Framing the North Hall Window and Door Openings.
10. Framing Mid Hall Window Openings.
11. Framing Main Hall Window Openings.
12. Framing South East Wing Window Openings.
13. Framing Main Hall Mem’s Restroom Window Openings.
14. Framing the Arched Window Opening in Mid Hall.
15-1. Radian Floor Manifolds Installation - Mid Hall and North Hall System.
15-2. Radian Floor Manifolds Installation - Main Hall and South East Wing System.
16. North Hall Down Spouts Installed.
17-1. Build Scaffolding Around Clerestory Window Area for Stucco Work.
|
17-3. Installed Weather-Resistive Barrier Paper.
|