Project update / October ( I )
1. Main Hall HVAC Ducting Completed. 1-1. Ducting for the return air.
1-2. Holes cut for the return vents.
1-3. Ducting for the West Wall.
1-4. Holes cut for the vents.
1-5. Ducting for the South Wall.
1-6. Holes cut for the vents.
1-7. Main Hall Ducting for the East Wall.
|
2. Mid Hall HVAC Ducting Completed.
2-1. Modify framing for HVAC vents.
2-2. Cutting holes in the ducting for the vents.
2-3. Holes cut for vent for Mid Hall System.
2-4. Return Ducting for Mid Hall System.
2-5. Indoor Unit for the Mid Hall System.
2-6. Ducting for the Mid Hall Storage.
3. Framing North Hall Bulk Head encasing A/C Vents.
4. Finishing Main Hall Ceiling Framing.
5. Start framing the North Hall window openings.
6. Start framing the Mid Hall window openings.
7. Start closing the infills.
7-1. Using electric pick to cut away the bull nose openings.
7-2. Fill and screw the plywood into the opening.
7-3. Exterior.
7-4. Interior.
7-5. Exterior.
7-6. Interior.
7-7. Exterior – All exterior surface will be covered by fiberglass mat gypsum sheathing. providing superior moisture and mold resistance.
7-8. Interior.
7-9. Exterior.
7-10. Interior.
|