Project update / March
1. Finished plumbing rough in on all restrooms, and inspection of all restrooms PASSED. |
2. The structural reinforcement for the Main Hall has been completed, inspected, and passed.
|
4. Demolition of "raised pad" completed.
|
5. Drill holes for the 4 piers as the foundation for the statue.
|
6. The hole for the statue foundation has been filled with Lean Concrete as per Structure Engineer of Record’s instruction.
|
7. Continue to remove metal window frames, and prep for installing new windows.
|
8. Cleaned out the North Hall for installing the Electrical Conduit, Diaz Electric has started installing the conduit for the electric.
|
9. Sack Construction will start installing the vapor barrier and 2” rigid insulation before pouring the concrete floor.
|
10. Original Roof.
11. The Day the Re-roofing Work Started.
11-1. Removing Clay Tiles Carefully to be Reused.
11-2. The Condition of the Existing Roof Deck.
12. Removing the Dry Rot / Damaged Roof Deck.
12-1. Replacing the Damaged Wood Deck with 2 Inches Thick Hardwood.
12-2. Re-building the Damaged Eaves of the Main Hall and Clerestory.
13. Covering the Repaired Wood Deck with ¾” Plywood.
14. Installing the Waterproofing Underlayment.
15. Installing Clay Tiles.
16. Installing Ridge Tiles.
16-1. Before.
16-2. After.
|