Project update / July

1. Continuing working on the footing for the Vestibule Foundation Slab.
1-1. Pipes not cut were wrapped.
Picture
1-2. Installing the anchoring steel plate for the store front posts.
Picture
Picture
2. Installing More Fire Sprinkler Piping in Mid Hall and Restrooms.
Picture
Picture
Picture
3. Finishing installing the clerestory windows.
Picture
Picture
Picture
4. Clean-up and shaping the plants on the west slope.
5. Installed Temporary Irrigation System on the West Slop Keeping the Plants Thriving.
6. Installing Main Hall Structure Reinforcement Steels.
Picture
Picture
Picture
7. Pour Concrete for Vestibule Footing.
Picture
8. Grading the Vestibule Area.
Picture
Picture
9. Trench for Utility Conduit and Lay the Conduit.
Picture
Picture
Picture
10. Installing Posts for the Store Front.
Picture
Picture
Picture
11. Installing Ceiling Insulation in the North Hall.
Picture
Picture