Project update / February
1. The demolition on the women's restroom floor in the South East Wing to make the elevation the same as the Main Hall has been done. |
2. The doors have been cut through the concrete wall for the same restroom.
|
3. The opening between the Main Hall and the Mid Hall has been cut.
|
4. The new entrances to the Mid Hall have has been cut, and the old bricks being saved to fill other openings.
|
5. The new entrance door to the Main Hall have been cut (larger than the other door allowing to move the statue in.)
|
6. The structure enhancement with 10 steel columns/beams in the Main Hall are being set and erected.
|
7. Removing all of the old steel window frames and the actual window measurements have been taken.
|
8. Filling in the basement in the Main Hall Men's Restroom.
|
9. The roof on the South East wing is being worked on.
|
10. The plumbing rough-in has been started and the plumbers are working on it daily.
|