Project update / August ( II )

3. Start Framing for the North Hall.
3-1. A Storage and a mechanical room framed.
Picture
Picture
3-2. Opening framed for windows.
Picture
Picture
3-3. Closing up an existing opening.
Picture
Picture
4. Finishing framing for North Hall.
Picture
Picture
Picture
Picture
5. Working on bracing and blocking of structure reinforcement details for the North Hall.
Picture
Picture
6. Framing Mid Hall and Mid Hall Storage area.
Picture
Picture
Picture
Picture
7. Start on the blocking reinforcing details for the structure reinforcement in Main Hall and Mid Hall:
Filling the gap between the newly installed steel beam and the ceiling with wood, welding on the 4" pieces of steel plate on one side of the stiffeners/kickers ceiling beams, screwing all of the 32 holes on the newly added 4" steel plate with 3 1/2" x ¼ SDS screws for each of the 35 newly installed steel beams..
Picture
Picture
8. Installing roof ventilation and eaves vent for Mid Hall.
Picture
Picture
9. Install rigid ceiling insulation in the Mid Hall.
Picture
Picture
Picture
10. Install rigid ceiling insulation in the Main Hall.
Picture
Picture