Project update / April ( I )

1. Finished laying the vapor barrier and insulation for the radiant floor in North Hall.
Picture
Picture
Picture
2. Installing Rebar for the concrete floor in the North Hall.
3. Completed the rough in for the radiant floor supply lines and PASSED the inspection for North Hall and Mid Hall.
Picture
4. Formed North Hall and Mid Hall for concrete.
Picture
5. The radiant floor heating tubing in the North Hall and Middle Hall has been installed and ready for inspection.
6. Passed the inspection for the radiant floor heating tubing in the North Hall and Middle Hall.
7. North Hall 1st Pour of the Concrete Floor.
Picture
8. Poured, Polishing and scored the 1st Half of North Hall.
9. Poured the 2nd half of North Hall.
Picture
10. Installing Electric Conduit in Mid Hall and Main Hall.
Picture
Picture
11. Removing Mid Hall restroom concrete floor to accommodate 2 inch grade in restroom area.
Picture
12. Mid Hall Grading Done.
Picture
Picture
Picture
13. Finished laying the vapor barrier, insulation and rebar for the radiant floor in Mid Hall.
Picture
Picture
14. Poured concrete floor in Mid Hall.
Picture
Picture