3. Completed the rough in for the radiant floor supply lines and PASSED the inspection for North Hall and Mid Hall.
|
5. The radiant floor heating tubing in the North Hall and Middle Hall has been installed and ready for inspection.
|
6. Passed the inspection for the radiant floor heating tubing in the North Hall and Middle Hall.
|
7. North Hall 1st Pour of the Concrete Floor.
|
8. Poured, Polishing and scored the 1st Half of North Hall.
|
9. Poured the 2nd half of North Hall.
|
10. Installing Electric Conduit in Mid Hall and Main Hall.
|
11. Removing Mid Hall restroom concrete floor to accommodate 2 inch grade in restroom area.
|
12. Mid Hall Grading Done.
|
13. Finished laying the vapor barrier, insulation and rebar for the radiant floor in Mid Hall.
|